Clear out all stored items from main hall-COMPLETE Replace Windows with Insulated Windows-COMPLETE Insulate Walls-COMPLETE Insulate Attic-COMPLETE Renovate bathroom 1 and make ADA compliant-COMPLETE Install Fire Alarm system-COMPLETE Replace Oil Heat System with New Gas-COMPLETE Upadate wiring-in progress Add Vinyl Siding-3/4 Complete Tie in to Town Sewer-COMPLETE Pave Parking Lot-COMPLETE Stripe Parking Lot-In progress Provide ADA Ramp-In progress Repair Front Steps-COMPLETE Paint Interior-COMPLETE Install new gutters-planned Install new kitchen-In progress
|